Notice No. | 369 |
---|---|
Notice Date | 2018-05-04 |
Contract Title | Technical consulting service for determining the characteristics(tracks, radius of maximum wind, maximum wind speed, etc.) of 100,000-year return period typhoons passing over the Kori NPP site |
Contract Overview |
A risk assessment analysis of typhoon wind and surge for a return internal of 100,000 years on a nuclear power plant on the Korean peninsula. Synthetic typhoon which can represent the broad climate state as analyzed over the period 1980-2017 will be generated and the characteristics of typhoon will be analyzed. Finally, the risk assessment will be conducted via approximately 30,000 synthetic typhoon tracks statistical analysis results. |
Estimated Value | USD 30,700 |
Expected Completion Date | 2018-05-11 |
Reason(s) for the Sole Sourcing |
The contractor is considered as the only company to be able to provide above mentioned technical consulting service for following reasons; - The contractor is the only orgainzation which has the technical-and man-power for re-generation and risk assessment for specific designated location from the results of the full scale typhoon model. - The contractor holds the person whose theoretical finding was referenced by NRC(NUREG/CR-7005 and 7134). - Only the contractor has previous experience for risk assessment for typhoon hazards. |
Company to be Contracted | Wind Risk Tech. LTD (USA) |
Name | 문경님 |
Dept | Project Support Department |
Tel | +82-54-421-3919 |
kimoon@kepco-enc.com | |