Comments on Sole Source Contract

Customer CenterComments on Sole Source Contract
Notice No. 410
Notice Date 2019-10-14
Contract Title Technical Consultation on Review of Applying Different Edition and Addenda between Construction Code and Material Code
Contract Overview 1) Review of ASME Code requirements for the application of 2007 Edition (including 2008 Addenda) of ASME Sec. II to 2004 Edition of ASME Sec. III specified for a nuclear power plant construction
2) Review of U.S. NRC regulatory positions
3) Preliminary report
4) Final report reflected review & comment
5) Presentation to Korea Institute of Nuclear Safety (Optional)
Estimated Value USD 47,250
Expected Completion Date 6 weeks from the contract
Reason(s) for the Sole Sourcing The consultation should be based on an understanding of the philosophy and background of the ASME Code requirements
The contractor is considered as the only company to be able to provide above mentioned technical consulting service for following reasons.
- The contractor has consulted for most of the nuclear utilities in the United States and Canada, as well as in Europe and Asia on ASME Code issues.
- The contractor holds the persons who served as chairman or vice chairman of the ASME Sec. III/XI Committee.
- The contractor has one of the most complete libraries of ASME Code books with comments on all the changes to the ASME Code from 1952 to the present.
Company to be Contracted - Reedy Engineering
Name 김도경
Dept - Material Engineering
Tel - +82-54-421-7861
email - junwoov@kepco-enc.com