New Start, New Standard
Comments on Sole Source Contract
Comments on Sole Source Contract
Notice No. | 410 |
---|---|
Notice Date | 2019-10-14 |
Contract Title | Technical Consultation on Review of Applying Different Edition and Addenda between Construction Code and Material Code |
Contract Overview |
1) Review of ASME Code requirements for the application of 2007 Edition (including 2008 Addenda) of ASME Sec. II to 2004 Edition of ASME Sec. III specified for a nuclear power plant construction 2) Review of U.S. NRC regulatory positions 3) Preliminary report 4) Final report reflected review & comment 5) Presentation to Korea Institute of Nuclear Safety (Optional) |
Estimated Value | USD 47,250 |
Expected Completion Date | 6 weeks from the contract |
Reason(s) for the Sole Sourcing |
The consultation should be based on an understanding of the philosophy and background of the ASME Code requirements The contractor is considered as the only company to be able to provide above mentioned technical consulting service for following reasons. - The contractor has consulted for most of the nuclear utilities in the United States and Canada, as well as in Europe and Asia on ASME Code issues. - The contractor holds the persons who served as chairman or vice chairman of the ASME Sec. III/XI Committee. - The contractor has one of the most complete libraries of ASME Code books with comments on all the changes to the ASME Code from 1952 to the present. |
Company to be Contracted | - Reedy Engineering |
Name | 김도경 |
Dept | - Material Engineering |
Tel | - +82-54-421-7861 |
- junwoov@kepco-enc.com | |
Attachments |
|