Comments on Sole Source Contract

Customer CenterComments on Sole Source Contract
Notice No. 434
Notice Date 2020-06-08
Contract Title Agreement for Environmental Impact Analysis for Gas to Power Project
Contract Overview Conduct Environmental Impact Assessment (EIA) study and preparation of an EIA report for the LNG Terminal
and 2,300MW combined power plant to be located in the Redondo Peninsula, Subic, Zambales
Estimated Value 5,824,000 PhP (Including VAT)
Expected Completion Date 120 days after the Contract
Reason(s) for the Sole Sourcing Considering the EIA study work scope and procedure it is mandatory to collect and analyze various site conditions in the Subic area
such as topographic, water resources, marine condition, air quality and so on.
Also in order to perform the socio module the contractor should contact with the people in the Barangay as well as
local government entities including health offices, so familiarization with the candidate area and people is necessary.

In addition, proper equipment and tools with experienced experts necessary for implementing field survey and modeling
should be basic requirement to perform the EIA study.
East Manila Georesearch Inc. is deemed to have aforesaid capability and experience since it has acquired
the Environmental Compliance Certificates (ECCs) for a power plant project which has been built in adjacent area,
therefore KEPCO E&C is to contract with East Manila Georesearch Inc.
Company to be Contracted East Manila Georesearch Inc.
Name Hyeon Nam
Dept Electrical, Instrumentation & Control Engineering Department
Tel +82 54-421-7648
email hnamkim@kepco-enc.com
Attachments
  • pdf 첨부파일 Attachment. Work Scope-EIA.pdf (76.21KB) Download