KEPCO E&C is diversifying the core capability of engineering to the power plant EPC (Engineering, Procurement, Construction) field.
KEPCO E&C has successfully performed the ‘EPC Expansion Project of the Takoradi T2 Combined Cycle Power Plant’ to open a new chapter in the diversification of the business to the power plant EPC field. In this project, we have expanded 2 HRSG, 1 120MW class steam turbine, sea water direct cooling structure, and more.
Furthermore, we have performed the expansion project of Ciprel Combined Cycle Power Plant in Cote d’Ivoire in EPC. In this project, to the 110MW class gas turbine of the existing power plant, we have added 2 HRSG, 1 steam turbine, and 1 Air Cooled Condenser (ACC) to convert into combined cycle power plant.
We are continuously expanding and strengthening the EPC businesses such as ‘EPC Project in Top Osan Combined Heat & Power Plant’, and ‘Procurement of Materials and Equipment for Tufanbeyli Coal Fired Power Plant in Turkey’.
Major Projects
Ghana Takoradi T2 & T1 Project

- Name of the Project : Expansion Project of the Takoradi T2 Electric Generating Facility
- Place of Construction : Takoradi, Ghana
- Construction Scale : Steam Turbine: 1 Unit, HRSG: 2 Units, Marine Work (HDPE Pipe 2.8km)
- Fuel Used : NG (Natural Gas)
- Contract Period : 2012. 7. – 2015. 12
- Customer : TICO (Takoradi International Company)
EPC Project for Top Osan Combined Heat & Power Plant

- Name of the Project : Top Osan Combined Heat & Power Plant Construction
- Place of Construction : 55, Hwangsae-ro 149beon-gil, Osan-si, Gyeonggi-do , Korea
- Construction Scale : 436 MW + 280 Gcal/hr, Gas Turbine: 1 Unit, Steam
- Turbine: 1 Unit, HRSG : 1 Unit, Transmission Line (345,154 KV)
- Substation Facilities : (345 KV.GIS 2 Bay)
- Fuel Used : LNG (Liquid Natural Gas)
- Contract Period : 2013. 11. – 2016. 03
- Customer : DSPower(SPC)
Cote d’Ivoire CIPREL IV Volet B PROJECT

- Name of the Project : CIPREL IV Volet B PROJECT
- Place of Construction : Abidjan, Cote d’Ivoire
- Construction Scale : HRSG: 2 Units, Steam Turbine: 1 Unit, ACC: 1 Unit
- Fuel Used : NG (Natural Gas)
- Contract Period : 2013. 9. – 2016. 03
- Customer: CIPREL (Compagnie Ivoirienne de Production d’Electricite)
Sudokwon Landfill Site Landfill Gas 55MW Power Plant

- Name of the Project : Electric Power Construction of the Sudokwon Landfill Site Landfill Gas Resource Project
- Place of Construction : Sudokwon Landfill Site,
58, Baekseok-dong, Seo-gu, Incheon-si - Construction Scale: 55 MW : 1 Unit + Transmission Line (Transmission & Distribution Voltage : 154KV, Transmission Line: 8km)
- Fuel Used : Landfill Gas
- Contract Period : 2004. 03. – 2016. 12
- Customer : Eco Energy(SPC)